Skip to main content

Mamquam WWTP UV Disinfection Upgrades

Location Squamish, BC, Canada
Owner District Of Squamish
Engineer Stantec Consulting Ltd.
Status Completed February 2017

This project commenced in October 2016 was completed by February 2017. The scope of work for this project consisted of a new cast-in-place concrete UV structure and installation of the new Wedeco UV Disinfection System at the current waste water treatment facility.  Included in this contract was the supply and installation of all process mechanical equipment, process pipework and valves, electrical and instrumentation equipment, cabling and devices as well as the supply and installation of a structural steel building over the new UV equipment. Several large diameter pipe tie-ins to the existing system were required.