The Corporation of the Township of Spallumcheen – Well #6 Upgrades
Carver was awarded the contract in late 2025 and mobilized to site in February 2026, with commissioning completed in September 2026.
The project consisted of the installation of a 100 hp well pump and associated components, along with the construction of a 5.4 m x 5.4 m masonry block building. The facility included a designated process and electrical rooms. The scope also included installation of all associated civil piping and tie-in to the existing water distribution system.