Victoria Road Stormwater Replacement
This project consisted of the removal and disposal of roughly 330m of existing PVC stormwater mains, 35m of 200mm catchbasin lead and 5 top inlet catch basins. Construction of approximately 335m of 375mm PVC stormwater main, 35m of 200mm catch basin leads, 8 top inlet batch basins and 5 manholes 1050Ø. The stormwater main consisted of open trench construction which involved saw-cutting, road sidewalk and driveway restoration and the addition of an asphalt multi-use path.
Carver will need to mobilize back to site once the gas permit has been acquired.