Victoria Road Stormwater Replacement

Location Summerland, British Columbia
Owner District of Summerland
Engineer Urban Systems Ltd.
Status In Progress

This project consisted of the removal and disposal of roughly 330m of existing PVC stormwater mains, 35m of 200mm catchbasin lead and 5 top inlet catch basins. Construction of approximately 335m of 375mm PVC stormwater main, 35m of 200mm catch basin leads, 8 top inlet batch basins and 5 manholes 1050Ø. The stormwater main consisted of open trench construction which involved saw-cutting, road sidewalk and driveway restoration and the addition of an asphalt multi-use path.

Carver will need to mobilize back to site once the gas permit has been acquired.